# The Hinkley Point C (Nuclear Generating Station) Order 2013, Paragraph 3: Impairment of efficiency of drainage work for flood defence purposes

Extent: E+W+S

If by reason of the construction of any consented work, or of the failure of any such work, the efficiency of any drainage work for flood defence purposes is impaired, or that drainage work is otherwise damaged, such impairment or damage shall be made good by the undertaker to the reasonable satisfaction of the Agency; and if the undertaker fails to do so within such reasonable period as the Agency may require by notice in writing to the undertaker, the Agency may make good such impairment or damage and recover from the undertaker the expense reasonably incurred by it in so doing.

---
Source: https://www.legislation.gov.uk/uksi/2013/648/schedule/15/paragraph/3 (the official version)
Page: https://openlegislation.uk/hinkley-point-c-nuclear-generating-station-order-2013/schedule-15/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.