# The Hinkley Point Harbour Empowerment Order 2012, Article 21: Harbour limits

Extent: E+W+S

(1) The limits of the harbour within which the Company shall exercise jurisdiction as the harbour authority and within which the powers of the harbour master shall be exercisable are—
(a) the seaward limits, that is to say, the area bounded by an imaginary line commencing at a point at ST1945046126, then extending in a straight line to a point at ST1873246621, then extending in a straight line to a point at ST1964046879, then in a straight line to a point at ST1964046153, then following the level of high water to the point of commencement; and
(b) the landward limits, that is to say—
(i) so much of the land lying within the limits of deviation of Work No. 1 as shown on the deposited plans and sections as is above the level of high water; and
(ii) all of the land lying within the limits of deviation of Work Nos. 4 to 9 as shown on the deposited plans and sections.
(2) The area described in paragraph (1)(a) is, for the purposes of identification only, shown edged by a black line on sheet no. 13 and, in the event that there is any discrepancy between the description of that area and the area shown on that sheet, the description shall prevail.
(3) In paragraph (1), a reference to a point is a reference to an Ordnance Survey National Grid reference point.

---
Source: https://www.legislation.gov.uk/uksi/2012/1914/article/21 (the official version)
Page: https://openlegislation.uk/hinkley-point-harbour-empowerment-order-2012/article-21
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.