# The Hinkley Point Harbour Empowerment Order 2012, Paragraph 11: Noise and vibration: control of noise during construction, maintenance and use

Extent: E+W+S

Before the commencement of the construction of the development, a noise and vibration management plan must be submitted to, and approved in writing by, the local planning authority which specifies the provision to be made for the control of noise and vibration arising from the construction, maintenance and use of the development. The plan must be implemented in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2012/1914/schedule/1/paragraph/11 (the official version)
Page: https://openlegislation.uk/hinkley-point-harbour-empowerment-order-2012/schedule-1/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.