# The Hinkley Point Harbour Empowerment Order 2012, Paragraph 26: Historic: scheduled monument management plan

Extent: E+W+S

(1) No construction of the development must commence until a monument management plan for Wick Barrow (SM No. 28), also known as Pixies Mound, (as shown at figure 22.1 of the environmental statement submitted with the application for this Order) has been submitted to, and approved in writing by, the local planning authority.
(2) The monument management plan must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2012/1914/schedule/1/paragraph/26 (the official version)
Page: https://openlegislation.uk/hinkley-point-harbour-empowerment-order-2012/schedule-1/paragraph-26
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.