(1) No construction work, or the delivery or removal of materials, is to take place outside the hours of—
(a) 0700 and 1830 hours on weekdays (excluding public holidays); and
(b) 0700 and 1300 hours on Saturdays and public holidays.
(2) Sub-paragraph (1) does not prevent outside such hours construction works, or the delivery or removal of materials, being carried out with the prior written approval of the relevant planning authority.

---