# The Hirwaun Generating Station Order 2015, Paragraph 24

Extent: E+W+S

For the protection of the utility undertakers referred to in this Part of this Schedule (save for National Grid, which is protected by and as defined in Part 1 of this Schedule, WPD, which is protected by and as defined in Part 2 of this Schedule and DCC, which is protected by and as defined in Part 7 of this Schedule), the following provisions have effect, unless otherwise agreed in writing between the undertaker and the utility undertakers concerned.

---
Source: https://www.legislation.gov.uk/uksi/2015/1574/schedule/7/paragraph/24 (the official version)
Page: https://openlegislation.uk/hirwaun-generating-station-order-2015/schedule-7/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.