Article 25 Acquisition of subsoil onlyI1
England, Wales and Scotland
The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of the land referred to in paragraph (1) of article 18 (compulsory acquisition of land etc.) or article 21 (compulsory acquisition of rights F1...) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.
Where the undertaker acquires any part of, or rights in, the subsoil of land under paragraph (1), the undertaker is not required to acquire an interest in any other part of the land.
The following do not apply in connection with the exercise of the power under paragraph (1) in relation to subsoil only—
Schedule 2A (counter-notice requiring purchase of land not in notice to treat) to the 1965 Act as modified by Schedule 7 (modification of compensation and compulsory purchase enactments for creation of new rights);
Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration) to the 1981 Act; and
Section 153(4A) (blighted land: proposed acquisition of part interest; material detriment test) of the Town and Country Planning Act 1990.
Paragraphs (2) and (3) do not apply where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building or factory.
Annotations
Textual amendments
- F1
Word in art. 25(1) omitted (31.1.2024) by virtue of The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.
Commencement
- I1
Art. 25 in force at 3.8.2023, see art. 1
Notes on the whole SI
Textual amendments
- F1
Word in preamble substituted (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.