# The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 10: Ecological management plan

Extent: E+W+S

(1) No stage of the connection works may commence until a written ecological management plan (which accords with the outline ecological management plan and the relevant recommendations of appropriate British Standards) for that stage of the connection works reflecting the survey results and ecological mitigation has been submitted to and approved by the relevant planning authority in consultation with the relevant SNCBs and (where works have potential to impact wetland habitats) the Environment Agency.
(2) The ecological management plan must include an implementation timetable for the relevant stage of the connection works and must be carried out as approved.

---
Source: https://www.legislation.gov.uk/uksi/2023/800/schedule/1/paragraph/10 (the official version)
Page: https://openlegislation.uk/hornsea-four-offshore-wind-farm-order-2023/schedule-1/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.