# The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 19: Construction traffic management plan

Extent: E+W+S

(1) No stage of the connection works or Work No. 5 may commence until written details of a construction traffic management plan (which accords with the outline construction traffic management plan) for that stage of the connection works or Work No. 5 has been submitted to and approved by the relevant planning authority in consultation with the relevant highway authorities (and approved by Network Rail in accordance with paragraph 5 of Part 4 of Schedule 9).
(2) The construction traffic management plan must be implemented as approved.

---