# The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 30: Requirement for written approval

Extent: E+W+S

Where the approval, agreement or confirmation of the Secretary of State, the relevant planning authority or another person is required under a requirement, that approval, agreement or confirmation must be given in writing.

---
Source: https://www.legislation.gov.uk/uksi/2023/800/schedule/1/paragraph/30 (the official version)
Page: https://openlegislation.uk/hornsea-four-offshore-wind-farm-order-2023/schedule-1/paragraph-30
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.