# The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 23: Piling restriction

Extent: E+W+S

In the event that driven or part driven pile foundations are to be used to install Work No. 3, no impact piling may be undertaken between 21 August and 23 October each year within the area of Work No. 3 as shown on the offshore works plans unless otherwise agreed in writing by the MMO after consultation with the relevant statutory nature conservation body.

---