# The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 26: Completion of construction

Extent: E+W+S

The undertaker must submit a close out report to the MCA and the UK Hydrographic Office within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following—
(a) a plan of the layout of installed export and inter-array cables, offshore substations and booster stations; and
(b) latitude and longitude coordinates of the location of export and inter-array cables, offshore substations and booster stations, provided as Geographical Information System data referenced to WGS84 datum.

---