# The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 11

Extent: E+W+S

The undertaker must carry out the predator eradication method as set out in the GCIMP approved by the Secretary of State in consultation with Natural England, the Alderney Wildlife Trust and the local planning authority. Work No. 1(a) and 1(b), Work No. 2(a), 2(b) and (c) and Work No. 3(a) must not commence until the GCIMP has been approved by the Secretary of State in accordance with paragraph 10, and at least 2 years have elapsed since the start of the predator eradication works.

---