# The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 2

Extent: E+W+S

Work Nos. 1, 2, 3, 4 and 5 together with any associated development offshore may not be commenced until a plan for the work of the H4 OOEG has been submitted to and approved by the Secretary of State, such plan to include—
(a) terms of reference of the H4 OOEG;
(b) details of the membership of the H4 OOEG which must include—
(i) the MMO and the relevant SNCB as core members for the offshore compensation measures;
(ii) the relevant local planning authority and Natural England as core members for the onshore compensation measures;
(iii) the RSPB, The Wildlife Trust and Alderney Wildlife Trust as advisory members, for both the onshore compensation measures and/or the offshore compensation measures subject to their area of expertise;
(c) details of the proposed schedule of meetings, timetable for preparation of the KCIMP and GCIMP and reporting and review periods;
(d) the dispute resolution mechanism and confidentiality provisions; and
(e) the scope of work to be limited to the topics for discussion as identified by the appointed chair to include in relation to the compensation measure, monitoring and adaptive management.

---
Source: https://www.legislation.gov.uk/uksi/2023/800/schedule/16/paragraph/2 (the official version)
Page: https://openlegislation.uk/hornsea-four-offshore-wind-farm-order-2023/schedule-16/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

