# The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 4

Extent: E+W+S

The undertaker must implement the measures set out in the KCIMP approved by the Secretary of State, unless otherwise agreed by the Secretary of State in consultation with the relevant SNCB, MMO and the relevant local planning authority. No operation of any turbine forming part of the authorised development may begin until the KCIMP has been approved by the Secretary of State and two full breeding seasons following the implementation of the measures set out in the KCIMP have taken place. For the purposes of this paragraph each breeding season is assumed to have commenced on 1 April in each year and ended on 30 September.

---
Source: https://www.legislation.gov.uk/uksi/2023/800/schedule/16/paragraph/4 (the official version)
Page: https://openlegislation.uk/hornsea-four-offshore-wind-farm-order-2023/schedule-16/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.