# The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 6: Line of orientation

Extent: E+W+S

The licensee shall not carry out, nor procure the carrying out of, the licensee’s works in any way that would prevent the undertaker from constructing and maintaining the wind turbine generators comprised in the authorised development in a layout consistent with the primary lines of orientation.

---
Source: https://www.legislation.gov.uk/uksi/2023/800/schedule/9/part/10/paragraph/6 (the official version)
Page: https://openlegislation.uk/hornsea-four-offshore-wind-farm-order-2023/schedule-9/part-10/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.