# The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 5: Coexistence and proximity agreement

Extent: E+W+S

If, at any time the undertaker plans to undertake the undertaker’s works and/or any other work which is within five hundred metres (500m) of the Johnston Assets, the undertaker shall notify the licensee and the undertaker and the licensee must, unless agreed otherwise, acting reasonably, agree and enter into a crossing and proximity agreement as soon as reasonably practicable.

---