# The Hornsea One Offshore Wind Farm (Amendment) Order 2016, Schedule: Revised plans


(1)
(2)
Old plans
Revised plans
Offshore HVAC Collector Substation. Rev A. DRW. No- UK04-080500-DWR-0009
Offshore HVAC Collector Substation Indicative Layout (Drawing no. SIDE11A)
Reactive Compensation Substation. Rev A. DRW. No- UK04-080500-DWR-0007
Offshore HVAC Reactive Compensation Substation Indicative Layout (Drawing no. SIDE13A)

---