# The Hornsea One Offshore Wind Farm Order 2014, Paragraph 20: North Coates airfield

Extent: E+W+S

No part of the authorised development is to commence within half a mile of the perimeter of the North Coates airfield until a plan to secure its safe operation during the construction and operation of the authorised project has been submitted to and approved by the Secretary of State following consultation by the Secretary of State with the operator of North Coates airfield and the Civil Aviation Authority.

---
Source: https://www.legislation.gov.uk/uksi/2014/3331/schedule/1/part/3/paragraph/20 (the official version)
Page: https://openlegislation.uk/hornsea-one-offshore-wind-farm-order-2014/schedule-1/part-3/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.