# The Hornsea One Offshore Wind Farm Order 2014, Paragraph 9: Implementation and maintenance of landscaping

Extent: E+W+S

(1) The landscape works must be carried out in accordance with the relevant scheme approved under requirement 8.
(2) Any tree or shrub planted as part of an approved landscape scheme that within a period of five years after planting, is removed, dies or becomes, in the opinion of the local planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless alternative timing or a different specimen is otherwise approved by the local planning authority.

---