If, due to stress of weather or any other cause, the master of a vessel determines that it is necessary to deposit—
(a) authorised deposits outside of Wind Farm Area 3 or disposal site reference HU206 (Hornsea Project One Subzone 1); or
(b) unauthorised deposits within or outside of Wind Farm Area 3 or disposal site reference HU206 (Hornsea Project One Subzone 1),
because the safety of human life and/or of the vessel is threatened, full details of the circumstances of the deposit shall be notified to the MMO within 48 hours.

---