If, due to stress of weather or any other cause, the master of a vessel determines that it is necessary to deposit the authorised deposits outside of the offshore Order limits or to deposit unauthorised deposits within or outside of the offshore Order limits because the safety of human life and/or of the vessel is threatened, full details of the circumstances of the deposit shall be notified to the MMO within 48 hours.

---