# The Hornsea One Offshore Wind Farm Order 2014, Paragraph 21: Offshore Decommissioning

Extent: E+W+S

No decommissioning activities shall commence until plans for the carrying out of such activities have been submitted to and approved in writing by the MMO.

---
Source: https://www.legislation.gov.uk/uksi/2014/3331/schedule/11/part/2/paragraph/21 (the official version)
Page: https://openlegislation.uk/hornsea-one-offshore-wind-farm-order-2014/schedule-11/part-2/paragraph-21
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

