# The Hornsea One Offshore Wind Farm Order 2014, Paragraph 102

Extent: E+W+S

Without prejudice to the generality of paragraph 100 of this Part of this Schedule, it shall not be reasonable for an approving party to withhold or delay any consent or approval under this Part of this Schedule in relation to specified work in, on, under, or over the grid connection land solely on the basis of thermal interaction between the circuit and any adjacent circuit, whether existing or proposed, where it has been demonstrated that there will be no material thermal interaction, which shall be deemed to have been demonstrated where the separation between such circuits is 6 metres or more (from the centre line of each circuit).

---