# The Hornsea One Offshore Wind Farm Order 2014, Paragraph 103

Extent: E+W+S

Without prejudice to the generality of paragraph 100, and in addition to the circumstances described in paragraph 102, it shall not be reasonable for the undertaker or C.GEN to withhold or delay any consent or approval under this Part of this Schedule in relation to specified work in, on, under, or over the crossing zones solely on the basis of thermal interaction where the plans of the specified work submitted under paragraph 93 demonstrate that all reasonable steps have been taken to minimise thermal interaction between the circuit and any other circuit, whether existing or proposed.

---