# The Hornsea One Offshore Wind Farm Order 2014, Paragraph 44

Extent: E+W+S

In this Part of this Schedule—
“accumulation” means any accumulation of silt or other material which constitutes an impediment to navigation
“construction” includes execution and placing, maintenance, extension, enlargement, alteration, replacement, relaying, and removal, (including for the avoidance of doubt the removal of the electrical circuits comprised in Work No. 6), and “construct” and “constructed” are to be construed accordingly;
“erosion” means any erosion of the bed or banks of the river Humber or of any jetty or other structure of whatever nature;
“plans” includes sections, descriptions, drawings and specifications; and
“specified work” means so much of Work No. 6 and any associated development or ancillary works as are within A. B. Port’s jurisdiction.

---
Source: https://www.legislation.gov.uk/uksi/2014/3331/schedule/12/paragraph/44 (the official version)
Page: https://openlegislation.uk/hornsea-one-offshore-wind-farm-order-2014/schedule-12/paragraph-44
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.