# The Hornsea One Offshore Wind Farm Order 2014, Paragraph 48

Extent: E+W+S

The undertaker must give to A. B. Ports not less than 14 days’ written notice of its intention to commence the construction of the specified works and, not more than 14 days after completion of such construction, must give to A. B. Ports written notice of such completion.

---
Source: https://www.legislation.gov.uk/uksi/2014/3331/schedule/12/paragraph/48 (the official version)
Page: https://openlegislation.uk/hornsea-one-offshore-wind-farm-order-2014/schedule-12/paragraph-48
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.