# The Hornsea One Offshore Wind Farm Order 2014, Paragraph 92

Extent: E+W+S

The undertaker must not under the powers of the Order acquire—
(a) new rights over the C.GEN relevant land; or
(b) new rights over the thermal buffer zone, except for the purposes of access and maintenance,
without the consent of C.GEN, such consent not to be unreasonably withheld or delayed but which may be given subject to reasonable conditions.

---
Source: https://www.legislation.gov.uk/uksi/2014/3331/schedule/12/paragraph/92 (the official version)
Page: https://openlegislation.uk/hornsea-one-offshore-wind-farm-order-2014/schedule-12/paragraph-92
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.