# The Hornsea One Offshore Wind Farm Order 2014, Schedule 5: Land in which only new rights etc., may be acquired

Extent: E+W+S

(1)
(2)
Number of land shown on land plans
Purpose for which rights may be acquired
1 – 2
10 – 14
To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 160 metre corridor within the Order Land and to obtain access for such purposes
3 – 9
16 – 21
To ground and lay anchor for vessels within the Order Land
15
22
407 – 408
To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within the Order Land and to obtain access for such purposes
23
409
To install, maintain and use an access track and to obtain access for such purposes
25 – 26
To install, retain, maintain and operate transition jointing bays for the connection of offshore cable circuits to onshore cable circuits and apparatus (and to impose requirements for their protection) within an up to 150 metre corridor within the Order Land and to obtain access for such purposes
27 – 29
57 – 58
63 – 66
68 – 72
74
77 – 80
87
91
94
97
104 – 105
107 – 108
111 – 113
122 – 126
128 – 130
133
140 – 141
145
148
151 – 152
154
156
162
164 – 171
173 – 178
180
183 – 185
187 – 192
196
199 – 200
205 – 209
212 – 213
216
218 – 220
227
232 – 233
235
238
240
242 – 243
245 – 247
251 – 258
261
267 – 268
271 – 272
274
277
279
283
287
293 – 294
296 – 297
314 – 315
319 – 320
324
331 – 332
337 – 338
346
351
353 – 354
357
359 – 362
364 – 365
368 – 370
373 – 375
378 – 380
383
386
390 – 397
400
403
To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 30 metre corridor within the Order Land and to obtain access for such purposes
37 – 40
To install, maintain and use an access track and to obtain access for the purposes only of maintaining and operating the authorised project
226
To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 30 metre corridor within the Order Land and to obtain access for such purposes but not extending to breaking open the surface of the Order Land
313
352
To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 30 metre corridor within the Order land
406
To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within the Order land and to install, maintain and use an access track and to obtain access for such purposes
410
415
To install, retain, maintain and operate services (and to impose requirements for their protection) within the Order land and to install, maintain and use an access track and to obtain access for such purposes

---
Source: https://www.legislation.gov.uk/uksi/2014/3331/schedule/5 (the official version)