# The Hornsea One Offshore Wind Farm Order 2014, Paragraph 6: Notifications and inspections

Extent: E+W+S

(1) The licence-holder shall ensure that—
(a) a copy of this licence and any subsequent amendments or revisions to it are provided to—
(i) all agents and contractors notified to the MMO in accordance with the conditions of this licence; and
(ii) the masters and transport managers responsible for the vehicles notified to the MMO in accordance with the conditions of this licence; and
(b) within 28 days of receipt of a copy of this licence those persons referred to in sub-paragraph (a) shall provide a completed confirmation form to the MMO confirming their understanding of the terms and conditions of this licence.
(2) Only those persons and vessels notified to the MMO in accordance with condition 16 are permitted to carry out the licensed activities.
(3) Copies of this licence shall also be available for inspection at the following locations—
(a) the licence-holder’s registered address;
(b) any site office located at or adjacent to the construction site and used by the licence-holder or its agents and contractors responsible for the loading, transportation or deposit for the authorised deposits; and
(c) on board each vessel or at the office of any transport manager with responsibility for vessels from which authorised deposits are to be made.
(4) The documents referred to in paragraph (1)(a) shall be available for inspection by an enforcement officer at the locations set out in paragraph (3) above at any time.
(5) The licence-holder must provide access, and if necessary appropriate transportation, to the offshore construction site or any other associated works or vessels to facilitate any inspection that the MMO considers necessary to inspect the works during construction and operation of the authorised scheme.
(6) The licence-holder must inform the MMO in writing at least five working days prior to the commencement of the licensed activities or any phase of them.
(7) Prior to the commencement of the licensed activities the licence-holder must publish in the Kingfisher Fortnightly Bulletin details of the vessel routes, timings and locations relating to the construction of the authorised scheme.
(8) The licence-holder shall ensure that a Notice to Mariners is issued at least ten days prior to the commencement of the licensed activities advising of the commencement of licensed activities within Wind Farm Area 2 and the expected vessel routes from the local service ports to the turbine locations.
(9) The Notices to Mariners must be updated and reissued not less frequently than weekly and supplemented with VHF radio broadcasts agreed with the MCA in accordance with the construction and monitoring programme approved under licence condition 13(2)(a). Copies of all notices shall be provided to the MMO.
(10) The licence-holder must notify—
(a) the UK Hydrographic Office of commencement (within two weeks), progress and completion (within two weeks) of the authorised scheme in order that all necessary amendments to nautical charts are made; and
(b) the MMO once the authorised scheme is completed and any required lighting or marking has been established.

---
Source: https://www.legislation.gov.uk/uksi/2014/3331/schedule/9/part/2/paragraph/6 (the official version)
Page: https://openlegislation.uk/hornsea-one-offshore-wind-farm-order-2014/schedule-9/part-2/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.