# The Hornsea Three Offshore Wind Farm Order 2020, Paragraph 17: Code of construction practice

Extent: E+W

(1) No phase of any works landward of MLWS may commence until for that phase a code of construction practice (which must accord with the outline code of construction practice) has been submitted to and approved by the relevant planning authority, in consultation with the Environment Agency, the relevant SNCBs, the relevant highway authority and, if applicable, the MMO.
(2) The term “commence” as used in requirement 17(1) shall include any onshore site preparation works.
(3) All construction works for each phase must be undertaken in accordance with the relevant approved code of construction practice.

---