# The Hornsea Three Offshore Wind Farm Order 2020, Paragraph 23: Onshore decommissioning

Extent: E+W

(1) Within three months of the cessation of commercial operation of the connection works an onshore decommissioning plan must be submitted to the relevant planning authority for approval unless otherwise agreed in writing by the relevant planning authority.
(2) The relevant planning authority must provide its decision on the onshore decommissioning plan required under requirement 23(1) within three months of submission of such plan unless otherwise agreed in writing by the relevant planning authority and the undertaker.
(3) The decommissioning plan must be implemented as approved unless otherwise agreed in writing by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2020/1656/schedule/1/paragraph/23 (the official version)
Page: https://openlegislation.uk/hornsea-three-offshore-wind-farm-order-2020/schedule-1/paragraph-23
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.