# The Hornsea Three Offshore Wind Farm Order 2020, Paragraph 24: Notification of generation of power

Extent: E+W

The undertaker shall notify the relevant planning authority and the MMO upon first generation of power from each phase of the authorised project not less than seven days after the occurrence of this event.

---