# The Hornsea Three Offshore Wind Farm Order 2020, Paragraph: In the county of Norfolk, districts of North Norfolk, Broadland and South Norfolk

Extent: E+W

Work No. 6— onshore connection works consisting of up to six cable circuits, ducts and between Work No. 5 and Work No. 7 landward of MHWS and onshore construction works;
Work No.7— onshore connection works consisting of—
(a) up to six cable circuits and associated electrical circuit ducts between Work No. 6 and Work No. 8;
(b) onshore construction works;
(c) up to six transition joint bays; and
(d) horizontal directional drilling launch pits;
Work No. 8— onshore connection works consisting of—
(a) up to six cable circuits and associated electrical circuit ducts to Work No. 11;
(b) onshore construction works;
(c) up to 440 link boxes; and
(d) up to 440 joint bays;
Work No. 9— onshore connection works consisting of the construction of an onshore HVAC booster station, together with onshore construction works;Work No. 10— onshore connection works consisting of an onshore HVDC/HVAC substation, including up to six cable circuits and electrical circuit ducts, and onshore construction works;Work No. 11— onshore connection works consisting of up to six cable circuits and electrical circuit ducts between Work No. 10 and Work No. 12 and onshore construction works;Work No. 12— onshore connection works consisting of up to six cable circuits and electrical circuit ducts between Work No. 11 and the Norwich Main National Grid substation, including a connection above ground and electrical engineering works within or around the National Grid substation buildings and compound, and onshore construction works;Work No. 13— a construction compound to support the construction of Work Nos. 8, 9, 10, 11, 12, 14 and 15;Work No. 14— temporary vehicular access tracks to serve Work Nos. 7, 8, 9, 10, 11, 12, 13 and 15; andWork No. 15— temporary storage areas to assist with the onshore connection works.

---
Source: https://www.legislation.gov.uk/uksi/2020/1656/schedule/1/part/1/paragraph/wrapper1n1 (the official version)
Page: https://openlegislation.uk/hornsea-three-offshore-wind-farm-order-2020/schedule-1/part-1/paragraph-wrapper1n1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.