# The Hornsea Three Offshore Wind Farm Order 2020, Paragraph 9

Extent: E+W

(1) The undertaker must colour all structures yellow (colour code RAL 1023) from at least highest astronomical tide to a height directed by Trinity House, or must colour the structure as directed by Trinity House from time to time.
(2) Subject to sub-paragraph (1) above, unless the MMO otherwise directs, the undertaker must ensure that the wind turbine generators are painted light grey (colour code RAL 7035).

---
Source: https://www.legislation.gov.uk/uksi/2020/1656/schedule/11/part/2/paragraph/9 (the official version)
Page: https://openlegislation.uk/hornsea-three-offshore-wind-farm-order-2020/schedule-11/part-2/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

