# The Hornsea Three Offshore Wind Farm Order 2020, Paragraph 14

Extent: E+W

No cable installation works in Work No. 2(c) and (d), Work No. 3(c) and (d) and Work No. 5 may be commenced until a SIP for each of the NNSSR and the WNNC has been approved in writing by the Secretary of State. Before approving the SIPs the Secretary of State must consult the MMO and Natural England and, in relation to the SIP for the NNSSR, the JNCC.

---
Source: https://www.legislation.gov.uk/uksi/2020/1656/schedule/14/paragraph/14 (the official version)
Page: https://openlegislation.uk/hornsea-three-offshore-wind-farm-order-2020/schedule-14/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

