  "url": "https://openlegislation.uk/hornsea-three-offshore-wind-farm-order-2020/schedule-9/paragraph-21",
  "json_url": "https://openlegislation.uk/hornsea-three-offshore-wind-farm-order-2020/schedule-9/paragraph-21.json",
  "legislation": "uksi/2020/1656",
  "legislation_title": "The Hornsea Three Offshore Wind Farm Order 2020",
  "legislation_url": "https://openlegislation.uk/hornsea-three-offshore-wind-farm-order-2020",
  "path": "schedule/9/paragraph/21",
  "kind": "paragraph",
  "number": "21",
  "heading": null,
  "text": "The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 36 (certification of plans and documents , etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in a format reasonably specified by Network Rail.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Sch. 9 Pt. 5 para. 21 comma inserted (21.5.2021) by The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch."
    },
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 9 Pt. 5 para. 21 in force at 22.1.2021, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2020/1656/schedule/9/paragraph/21",
    "retrieved_at": "2026-10-28T22:19:02.788189+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}