# The Hornsea Three Offshore Wind Farm Order 2020, Paragraph 17: Notices

Extent: E+W

The plans submitted to National Grid by the undertaker pursuant to paragraphs 9(1) and 10(1) must be sent to National Grid Plant Protection at plantprotection@nationalgrid.com or such other address as National Grid may from time to time appoint instead for that purpose and notify to the undertaker in writing.

---
Source: https://www.legislation.gov.uk/uksi/2020/1656/schedule/9/part/2/paragraph/17 (the official version)
Page: https://openlegislation.uk/hornsea-three-offshore-wind-farm-order-2020/schedule-9/part-2/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.