# The Hornsea Three Offshore Wind Farm Order 2020, Paragraph 13

Extent: E+W

Anglian Water must give the undertaker reasonable notice of any claim or demand pursuant to paragraph 11 and must consider its representations before proceeding further in respect of the claim or demand.

---
Source: https://www.legislation.gov.uk/uksi/2020/1656/schedule/9/part/6/paragraph/13 (the official version)
Page: https://openlegislation.uk/hornsea-three-offshore-wind-farm-order-2020/schedule-9/part-6/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.