# The Hornsea Three Offshore Wind Farm Order 2020, Paragraph 14

Extent: E+W

The undertaker must pay to Boreas the reasonable expenses incurred by Boreas in connection with the approval of plans, inspection of any specified works or the alteration or protection of any apparatus or the proposed Norfolk Boreas Cable Corridor.

---
Source: https://www.legislation.gov.uk/uksi/2020/1656/schedule/9/part/9/paragraph/14 (the official version)
Page: https://openlegislation.uk/hornsea-three-offshore-wind-farm-order-2020/schedule-9/part-9/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.