# The Hornsea Two Offshore Wind Farm Order 2016, Paragraph 9: Implementation and maintenance of landscaping

Extent: E+W+S

(1) Landscape works must be carried out in accordance with the relevant landscape scheme approved under Requirement 8.
(2) Any tree or shrub planted as part of an approved landscape scheme that within a period of 5 years after planting, is removed, dies or becomes, in the opinion of the local planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless alternative timing or a different specimen is otherwise approved by the local planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2016/844/schedule/1/paragraph/9 (the official version)
Page: https://openlegislation.uk/hornsea-two-offshore-wind-farm-order-2016/schedule-1/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

