# The Hornsea Two Offshore Wind Farm Order 2016, Paragraph 10

Extent: E+W+S

The fact that any work or thing has been executed or done by the relevant undertaker in accordance with a plan approved or deemed to be approved by the drainage authority, or to its satisfaction, or in accordance with any directions or award of an arbitrator, does not relieve the relevant undertaker from any liability under this Part.

---
Source: https://www.legislation.gov.uk/uksi/2016/844/schedule/12/part/1/paragraph/10 (the official version)
Page: https://openlegislation.uk/hornsea-two-offshore-wind-farm-order-2016/schedule-12/part-1/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.