# The Hornsea Two Offshore Wind Farm Order 2016, Paragraph 4

Extent: E+W+S

No works comprising any part of the authorised development or the operation of the authorised undertaking which would have an effect in full or in part on the operation, maintenance, repair, replacement and abandonment of the pipeline and access to it may be commenced until plans and sections in respect of the works submitted under paragraph 3 have been approved by ConocoPhillips.

---
Source: https://www.legislation.gov.uk/uksi/2016/844/schedule/12/part/10/paragraph/4 (the official version)
Page: https://openlegislation.uk/hornsea-two-offshore-wind-farm-order-2016/schedule-12/part-10/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.