# The Hornsea Two Offshore Wind Farm Order 2016, Paragraph 12

Extent: E+W+S

Any consent or approval of an approving party required under this Part—
(a) must not be unreasonably withheld or delayed; and
(b) may be given subject to reasonable conditions.

---
Source: https://www.legislation.gov.uk/uksi/2016/844/schedule/12/part/11/paragraph/12 (the official version)
Page: https://openlegislation.uk/hornsea-two-offshore-wind-farm-order-2016/schedule-12/part-11/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.