# The Hornsea Two Offshore Wind Farm Order 2016, Paragraph 13

Extent: E+W+S

Any consent or approval of an approving party required under this Part is deemed to have been given if it is neither given nor refused within 28 days beginning with the date on which the application for consent or approval was submitted to the approving party.

---
Source: https://www.legislation.gov.uk/uksi/2016/844/schedule/12/part/11/paragraph/13 (the official version)
Page: https://openlegislation.uk/hornsea-two-offshore-wind-farm-order-2016/schedule-12/part-11/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.