# The Hornsea Two Offshore Wind Farm Order 2016, Paragraph 4

Extent: E+W+S

(1) The promoting party must give to the approving party not less than 28 days’ written notice of its intention to commence the construction of any specified works and at the same time must submit plans for the specified works to the approving party.
(2) Not more than 14 days after completion of the construction of the specified works, the promoting party must give the approving party written notice of such completion.

---