In this Part—
“A. B. Ports” means Associated British Ports;
“accumulation” means any accumulation of silt or other material that constitutes an impediment to navigation;
“construction” includes execution and placing, maintenance, extension, enlargement, alteration, replacement, relaying, and removal (including the removal of the electrical circuits comprised in Work Nos. 6A and 6B); and “construct” and “constructed” must be construed accordingly;
“erosion” means any erosion of the bed or banks of the River Humber or of any jetty or other structure of whatever nature;
“plans” includes sections, descriptions, drawings and specifications;
“relevant undertaker” means—
(a) in relation to specified works that is Project A works or associated development or ancillary works relating to Project A works, Optimus Wind;
(b) in relation to specified works that is Project B works or associated development or ancillary works relating to Project B works, Breesea; and
(c) in relation to specified works that is shared works or associated development or ancillary works relating to shared works, Optimus Wind and Breesea;
“specified works” means so much of Work Nos. 6A and 6B and any associated development or ancillary works as are within A. B. Ports’ jurisdiction.

---
Source: https://www.legislation.gov.uk/uksi/2016/844/schedule/12/part/5/paragraph/2 (the official version)
Page: https://openlegislation.uk/hornsea-two-offshore-wind-farm-order-2016/schedule-12/part-5/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.