# The Hornsea Two Offshore Wind Farm Order 2016, Paragraph 15

Extent: E+W+S

Any difference or dispute arising between the undertaker and Anglian Water under this Part must, unless otherwise agreed in writing between the undertaker and Anglian Water, be determined by arbitration in accordance with article 41.

---
Source: https://www.legislation.gov.uk/uksi/2016/844/schedule/12/part/6/paragraph/15 (the official version)