# The Hornsea Two Offshore Wind Farm Order 2016, Paragraph 16: Offshore decommissioning

Extent: E+W+S

(1) No decommissioning activities may commence until a plan for the carrying out of the activities has been submitted to and approved in writing by the MMO.
(2) The plan must be submitted for approval at least 4 months before the intended start of the decommissioning activities, except where otherwise stated or unless otherwise agreed in writing by the MMO.
(3) The plan must be implemented as approved.

---