# The Hornsea Two Offshore Wind Farm Order 2016, Paragraph 17: Amendments to approved plans, etc.

Extent: E+W+S

(1) Where any Condition requires the licensed activities to be carried out in accordance with any plan, programme, code, statement, protocol scheme or details (the “plan”) approved by the MMO, the approved plan must be taken to include any amendment to the plan that may subsequently be approved in writing by the MMO.
(2) Any amendment to the plan must be in accordance with the principles and assessments set out in the environmental statement, and approval for an amendment may be given only where it has been demonstrated to the satisfaction of the MMO that amendment is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

---
Source: https://www.legislation.gov.uk/uksi/2016/844/schedule/9/paragraph/17 (the official version)
Page: https://openlegislation.uk/hornsea-two-offshore-wind-farm-order-2016/schedule-9/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.